End of November we were called by a German client as they were facing a problem at the LNG terminal in Brunsbüttel. This terminal is located in the North of Germany, along the Elbe river, close to Hamburg.
The client had several mooring hook units which have been rejected after an inspection. With a ship coming in within a few weeks, Straatman was asked to deliver new triple Quick Release Mooring Hook units in just three weeks. We had several units on stock in our factory, due to a delayed project, which we were able to rebuilt to meet the specs of this client. With the tight time schedule in mind, the complete Straatman team did the outmost to fulfill this almost impossible task. And with success! The units were delivered within the requested three weeks. Glad en proud that we were able to help out!
Please contact us, we will tell you more about it! Fill in your details below. We aim to give you a response within one working day.